  • pana-bam
  • slideno

Downstream

Gas Pressure reducing station

The subject of the contract:
                      Complete construction of a gas pressure reducing station (CGS) in Shiraz Petrochemical
The employer:
                      Fars province Gas Company
The location of done:
                      Shiraz Petrochemical(south of Iran)
Duration of the contract:
                      6 Months
The start of the contract:
                      February 17, 2008
The price of the contract:
                      680.000 $.

FARAVARESH Company Maintenance & repairs

The subject of the contract:
                       maintenance, repairs, supplies, spare parts construction and installation of rotating machinery sensitive and semi- sensitive devices, including pumps, compressors and turbines.
The employer:
                      IMAM harbor (BANDARE – IMAM) petrochemical
The location of done:
                      MAHSHAHR petrochemical (working – site) Region.
Duration of the contract:
                      3 years.
The start of the contract:
                      November 22, 2005
The price of the contract:
                      4,000,000 $.

TONDGOOYAN Company Maintenance & Repairs

The subject of the contract:
                            maintenance, repairs, spare parts supply and installation of pumps, compressors and turbines of TONDGOOYAN petrochemical company
The employer:
                            TONDGOOYAN petrochemical company.
The location of done:
                            BANDAR – E - MAHSHAHR (MAHSHAR Harbor) petrochemical Region.
Duration of the contract:
                            3 YEARS
The start of the project:
                            March 6, 2007
The price of the contract:
                            3.250,000$